Work on Rundu weather office starts

27 May 2019 | Infrastructure

The works ministry has appointed Bongi and Prince Trading to complete the construction of the outstanding and shoddy works done at meteorological office at the Rundu airport which was abandoned by the initial contractor.

On Thursday last week, Bongi and Prince Trading was handed the site to complete all the outstanding civil works, likely to be carried out in the next two months.

This comes after the works minister, John Mutorwa, intervened in the matter when he visited the site in March. A dismayed Mutorwa was not convinced by the explanations given by the ministry's officials as to why the N$5.7-million project was an abandoned site while the contractor was already paid N$5.4 million.

“I am disappointed because someone was paid with taxpayers' money to construct this infrastructure, but they have not delivered as per the agreement,” Mutorwa said during a site visit in March.

“It is this don't-care attitude which is costing government a lot of money. There are quite a number of capital projects under the ministry of works that I am aware of that are incomplete, but people are very fast to write out cheques.”

The tender to construct the meteorological service office was initially awarded to Rundu-based Fermour Investment CC in 2013 and it was expected to be completed by 21 March 2014.

The completion date was later moved to 19 June 2015, however, the contractor could not complete the project by that time either and eventually abandoned the site. The contract was only terminated on 18 October 2018.

It was on that basis Mutorwa ordered his ministry's officials to work around the clock to ensure that all processes are followed for securing a new contractor to complete the outstanding works and for the office to become operational.

The project is said to be 90% complete and the outstanding work includes the electrification of the building, the installation of air conditioners, as well as a storm water channel, and dealing with several minor defects.

The region's meteorological staff are currently operating from a house in one of Rundu's townships.

KENYA KAMBOWE

Similar News

 

Spotlight on financing water infrastructure

1 day - 17 July 2019 | Infrastructure

Global and local experts are converging in Windhoek this week for a roundtable discussion on financing water projects. The event is initiated by Open Africa...

Land is too expensive

2 weeks ago - 04 July 2019 | Infrastructure

The Namibian government has recognised that a large section of people still do not have access to land and decent shelter because it is unaffordable,...

N$14m spent on housing, land in Kunene

2 weeks ago - 03 July 2019 | Infrastructure

While acknowledging that economic woes have not spared any of the 14 regions – the Kunene has recorded progress in the areas of infrastructure development,...

NHE ta tala komilandu omipe

3 weeks ago - 24 June 2019 | Infrastructure

Ehangano lyoNational Housing Enterprise otali konaakona onkalo yokutula miilonga omulandu gwohiila nokumona uumwene wegumbo, ihe inali holola natango kutya uunake omulandu ngoka tagu vulu okutulwa...

NHE studying lease-to-own model

3 weeks ago - 21 June 2019 | Infrastructure

OGONE TLHAGEThe National Housing Enterprise is studying the possibility of introducing a lease-to-own option but has not indicated when it will make a pronouncement on...

RA hamstrung

3 weeks ago - 21 June 2019 | Infrastructure

The Roads Authority (RA) says it does not have adequate funding for the rehabilitation and maintenance of national roads, and that the road-user charges collected...

Millions spent on unfinished govt office

4 weeks ago - 20 June 2019 | Infrastructure

A N$16 million fisheries ministry infrastructure project in Rundu, which has been under construction since 2012, is still standing incomplete, resulting in officials operating from...

'Missing millions' mystery at Okahao

4 weeks ago - 19 June 2019 | Infrastructure

The upgrading and renovation work at the Okahao district hospital, which had been abandoned eight years amid allegations that the contractor had received an upfront...

Houses, drought relief food not campaign strategy

4 weeks ago - 18 June 2019 | Infrastructure

People should not see houses built for them as a way for the ruling party to campaign for the upcoming election, but rather as development...

Work on Rundu weather office starts

1 month - 27 May 2019 | Infrastructure

The works ministry has appointed Bongi and Prince Trading to complete the construction of the outstanding and shoddy works done at meteorological office at the...

Latest News

Geingob stirs pot

3 hours ago | Politics

President Hage Geingob is meeting Swapo regional leaders across the country in the afternoons, after his ongoing town hall and regional meetings with the public.In...

Mujoro denies dodging 'independent' prickly...

3 hours ago | Politics

Electoral Commission of Namibia (ECN) chief electoral officer Theo Mujoro has denied dodging the prickly subject of independent candidates standing in elections in the country,...

Respect is a two-way street

3 hours ago | Columns

The ongoing debate unfolding in the National Assembly, which puts social cohesion in the spotlight, is quite interesting. For far too long we have observed...

Vendors in despair

3 hours ago | Agriculture

Mahangu flour vendors operating at various open markets in Rundu are struggling to pay back loans they took to purchase unprocessed grain from farmers, because...

State sued for N$3.8 million

3 hours ago | Justice

A man who was cleared of murder and robbery charges after he had spent more than five years in jail awaiting the completion of his...

Oshakati abattoir to reopen soon

3 hours ago | Agriculture

KIAT Investment Holdings, which has been awarded a tender to manage the Oshakati abattoir, says the plant will soon resume operations.This will be a relief...

NNFU sheds regional functions

3 hours ago | Agriculture

The Namibia National Farmers Union (NNFU) has underwent a restructuring exercise that has seen it shed some its regional operations.NNFU executive director Mwilima Mushokobanji said...

'We are not fighting'

3 hours ago | Government

President Hage Geingob held a town hall meeting in Mariental on Monday, and was in Keetmanshoop yesterday, where he assured residents that his administration is...

B1 City fraud accused loses...

3 hours ago | Justice

Hafeni Nghinamwaami, one the three businesspeople implicated in the fraud and corruption case surrounding the B1 City property development project, is without legal representation after...

Load More