Millions spent on unfinished govt office

20 June 2019 | Infrastructure

A N$16 million fisheries ministry infrastructure project in Rundu, which has been under construction since 2012, is still standing incomplete, resulting in officials operating from dilapidated rented offices.

According to the ministry the Kavango East regional office project has stalled because the contractor, Africa Civil Engineering, which was handed the site on 7 August 2015 to complete remaining work, has decided to inflate the price, which the ministry is not prepared to tolerate.

The works ministry is currently in the process of terminating the contract for this reason.

Executive City Construction was the initial contractor in 2012, until their contract was terminated for failing to carryout and complete the work as per the original scope.

“The project has gone for determination of contract, hence is not complete due to the price escalation, which is not permitted. Therefore the Ministry of Works and Transport is determining the contract of the contractor,” the fisheries ministry said in its response when contacted for comment.

It was reported in May last year that Africa Civil Engineering would complete the project by the end of 2018.

At the time Africa Civil Engineering's Petrus Kapula was quoted by New Era saying they have demonstrated their capacity to complete the project.

“We have demonstrated our capacity and capability to the ministry to conclude this project. Once everything and all agreements are in place, we will probably finish this project within six to seven months,” Kapula said.

It was further revealed that Africa Civil Engineering was paid about N$5.8 million for work done from 7 August 2015 to 7 July 2017.

About N$643 000 was retained by the works ministry, which was to be paid once the project was completed. Attempts to get comment from Kapula since last Friday proved futile as he was unreachable on his cellphone.

Africa Civil Engineering is currently constructing the N$7 million Kavango East Swapo office at Rundu, which has been delayed and was expected to be completed by April this year.

Namibian Sun visited fisheries office site and was greeted by a security guard, who was guarding the incomplete structures.

This was followed up by a visit to the Namibia Industrial Development Agency (NIDA) offices, formerly known as Namibia Development Corporation (NDC), where the ministry has been renting 13 offices and two storerooms for its officials for more than a decade.

The officials expressed their dissatisfaction with their working environment, as some plug sockets and the lights are not working and space is limited.

“As you can see the lights are not working and this is not my office; I just moved in here because in my office the plug is not functioning for me to connect my computer,” one official said on condition of anonymity.

“We are not informed about the incomplete office you are enquiring about, but all I can say is that we cannot carry out our work effectively.”

The ministry explained they are faced with a number of challenges at the rented premises.

“The Ministry of Fisheries and Marine Resources is currently renting offices from the NDC in Rundu for the 17 staff members of the DoAIF (directorate of aquaculture and inland fisheries) and operations. These offices do not have lab facilities for research and ponds for demonstration. Also lacking is a proper internet and telephone system,” ministry deputy director Elizabeth Swartz said. Swartz said the Kamutjonga Inland Fisheries Institute at Divundu is currently performing the research and demonstration function in Kavango East. Namibian Sun understands that once the office project is complete it will house an office building, ablution block, workshop, wash bay and net drying facility, a fish feed store, a boat, a trailer storage facility, garages, a generator room and a guard house.

The regional office will also offer installations of specialist services, equipment and associated ancillary site work.

KENYA KAMBOWE

Similar News

 

Spotlight on financing water infrastructure

5 days ago - 17 July 2019 | Infrastructure

Global and local experts are converging in Windhoek this week for a roundtable discussion on financing water projects. The event is initiated by Open Africa...

Land is too expensive

2 weeks ago - 04 July 2019 | Infrastructure

The Namibian government has recognised that a large section of people still do not have access to land and decent shelter because it is unaffordable,...

N$14m spent on housing, land in Kunene

2 weeks ago - 03 July 2019 | Infrastructure

While acknowledging that economic woes have not spared any of the 14 regions – the Kunene has recorded progress in the areas of infrastructure development,...

NHE ta tala komilandu omipe

4 weeks ago - 24 June 2019 | Infrastructure

Ehangano lyoNational Housing Enterprise otali konaakona onkalo yokutula miilonga omulandu gwohiila nokumona uumwene wegumbo, ihe inali holola natango kutya uunake omulandu ngoka tagu vulu okutulwa...

NHE studying lease-to-own model

1 month - 21 June 2019 | Infrastructure

OGONE TLHAGEThe National Housing Enterprise is studying the possibility of introducing a lease-to-own option but has not indicated when it will make a pronouncement on...

RA hamstrung

1 month - 21 June 2019 | Infrastructure

The Roads Authority (RA) says it does not have adequate funding for the rehabilitation and maintenance of national roads, and that the road-user charges collected...

Millions spent on unfinished govt office

1 month - 20 June 2019 | Infrastructure

A N$16 million fisheries ministry infrastructure project in Rundu, which has been under construction since 2012, is still standing incomplete, resulting in officials operating from...

'Missing millions' mystery at Okahao

1 month - 19 June 2019 | Infrastructure

The upgrading and renovation work at the Okahao district hospital, which had been abandoned eight years amid allegations that the contractor had received an upfront...

Houses, drought relief food not campaign strategy

1 month - 18 June 2019 | Infrastructure

People should not see houses built for them as a way for the ruling party to campaign for the upcoming election, but rather as development...

Work on Rundu weather office starts

1 month - 27 May 2019 | Infrastructure

The works ministry has appointed Bongi and Prince Trading to complete the construction of the outstanding and shoddy works done at meteorological office at the...

Latest News

Namibia gets more Welsh help

6 hours ago | Sports

JESSE JACKSON KAURAISA The Namibia Rugby Union (NRU) has acquired the services of Welsh Premiership boss Dale McIntosh to assist his counterpart Phil Davies with...

ACC probes Omuthiya

6 hours ago | Government

The Anti-Corruption Commission (ACC) is investigating alleged corrupt practices at the Omuthiya town council after some Swapo members laid complaints against their representatives.Swapo Party political...

Governor's advisor causes scandal in...

6 hours ago | Government

The governor for the Oshana Region, Elia Irimari, reportedly sent his special advisor, Michael Mwinga, home from an official visit to Angola for allegedly causing...

We have guaranteed poverty

6 hours ago | Opinion

More than 10 years ago there was concern over the growing numbers of orphans and vulnerable children in the country. During the time of Nangolo...

Shikongo calls for more support

6 hours ago | Sports

Debmarine Namibia chief executive Otto Shikongo has called on corporate private entities and parastatals to join the government in order to develop the youth in...

Big ups to Debmarine Namibia

6 hours ago | Sports

JESSE JACKSON KAURAISA I pen this with sincere gratitude towards Debmarine Namibia for sponsoring the financially struggling school sports fraternity.It...

Renewed plea for 2% donation

6 hours ago | Disasters

A public notice signed by cabinet secretary George Simataa, dated Thursday last week, makes a “humble appeal to all Namibians to donate up to 2%...

N$60k robbed from Ondangwa businesswoman...

6 hours ago | Crime

No arrest or recovery has been made in connection with a N$60 000 robbery at Ondangwa on Monday morning.The police in the Oshana Region reported...

Media get lukewarm scorecard

6 hours ago | Business

A home-grown analysis of the Namibian media landscape has identified a number of issues that detract from quality journalism and trust in the media. Among...

Load More