Millions spent on unfinished govt office

20 June 2019 | Infrastructure

A N$16 million fisheries ministry infrastructure project in Rundu, which has been under construction since 2012, is still standing incomplete, resulting in officials operating from dilapidated rented offices.

According to the ministry the Kavango East regional office project has stalled because the contractor, Africa Civil Engineering, which was handed the site on 7 August 2015 to complete remaining work, has decided to inflate the price, which the ministry is not prepared to tolerate.

The works ministry is currently in the process of terminating the contract for this reason.

Executive City Construction was the initial contractor in 2012, until their contract was terminated for failing to carryout and complete the work as per the original scope.

“The project has gone for determination of contract, hence is not complete due to the price escalation, which is not permitted. Therefore the Ministry of Works and Transport is determining the contract of the contractor,” the fisheries ministry said in its response when contacted for comment.

It was reported in May last year that Africa Civil Engineering would complete the project by the end of 2018.

At the time Africa Civil Engineering's Petrus Kapula was quoted by New Era saying they have demonstrated their capacity to complete the project.

“We have demonstrated our capacity and capability to the ministry to conclude this project. Once everything and all agreements are in place, we will probably finish this project within six to seven months,” Kapula said.

It was further revealed that Africa Civil Engineering was paid about N$5.8 million for work done from 7 August 2015 to 7 July 2017.

About N$643 000 was retained by the works ministry, which was to be paid once the project was completed. Attempts to get comment from Kapula since last Friday proved futile as he was unreachable on his cellphone.

Africa Civil Engineering is currently constructing the N$7 million Kavango East Swapo office at Rundu, which has been delayed and was expected to be completed by April this year.

Namibian Sun visited fisheries office site and was greeted by a security guard, who was guarding the incomplete structures.

This was followed up by a visit to the Namibia Industrial Development Agency (NIDA) offices, formerly known as Namibia Development Corporation (NDC), where the ministry has been renting 13 offices and two storerooms for its officials for more than a decade.

The officials expressed their dissatisfaction with their working environment, as some plug sockets and the lights are not working and space is limited.

“As you can see the lights are not working and this is not my office; I just moved in here because in my office the plug is not functioning for me to connect my computer,” one official said on condition of anonymity.

“We are not informed about the incomplete office you are enquiring about, but all I can say is that we cannot carry out our work effectively.”

The ministry explained they are faced with a number of challenges at the rented premises.

“The Ministry of Fisheries and Marine Resources is currently renting offices from the NDC in Rundu for the 17 staff members of the DoAIF (directorate of aquaculture and inland fisheries) and operations. These offices do not have lab facilities for research and ponds for demonstration. Also lacking is a proper internet and telephone system,” ministry deputy director Elizabeth Swartz said. Swartz said the Kamutjonga Inland Fisheries Institute at Divundu is currently performing the research and demonstration function in Kavango East. Namibian Sun understands that once the office project is complete it will house an office building, ablution block, workshop, wash bay and net drying facility, a fish feed store, a boat, a trailer storage facility, garages, a generator room and a guard house.

The regional office will also offer installations of specialist services, equipment and associated ancillary site work.

KENYA KAMBOWE

Similar News

 

Fire kills one, destroys vessel

3 days ago - 19 August 2019 | Infrastructure

A man was killed when the hake trawler Ocean Tide moored at the jetty of Seawork Fish Processors in Walvis Bay caught fire below deck...

Bypass cuts deep

3 days ago - 19 August 2019 | Infrastructure

Residents of Vergenoeg, an 'illegal' settlement on the western outskirts of Okahandja, held a community meeting on Saturday afternoon. The purpose was to discuss the...

Air Nam flight delays due to grounded pilots

6 days ago - 16 August 2019 | Infrastructure

Complaints are flooding in from frustrated Air Namibia customers who say they had to spend hours at Hosea Kutako International Airport (HKIA) because of delayed...

Millions for Windhoek’s informal settlements

1 week ago - 15 August 2019 | Infrastructure

The ministry of urban and rural development has set aside N$50 million to improve the living conditions of Windhoek’s informal settlements residents for the 10...

CoW delivers zero serviced plots in 2017/18

1 week ago - 13 August 2019 | Infrastructure

Despite setting sights on delivering 430 serviced erven for residential, business and institutional purposes during the 2017/18 financial year, the City of Windhoek (CoW) failed...

RFA considers toll roads

1 week ago - 09 August 2019 | Infrastructure

The Road Fund Administration (RFA) wants to investigate the viability of tolling Namibian roads as a potential additional revenue stream to the Road User Charging...

Rail limits Namport

2 weeks ago - 02 August 2019 | Infrastructure

While the expansion of the Walvis Bay port has been welcomed as a boon for the economy, the lack of a modern rail line to...

Zim dry port inaugurated

3 weeks ago - 29 July 2019 | Infrastructure

Zimbabwean president Emmerson Mnangagwa inaugurated his country's dry port facility in Walvis Bay on Friday. This formed part of his official state visit to Namibia....

Spotlight on financing water infrastructure

1 month - 17 July 2019 | Infrastructure

Global and local experts are converging in Windhoek this week for a roundtable discussion on financing water projects. The event is initiated by Open Africa...

Land is too expensive

1 month - 04 July 2019 | Infrastructure

The Namibian government has recognised that a large section of people still do not have access to land and decent shelter because it is unaffordable,...

Latest News

N$600m down the drain

6 hours ago | Justice

Any hopes of Namibia recovering the over N$600 million lost in the Government Institutions Pension Fund (GIPF) scandal have been dashed. Prosecutor-General Martha Imalwa confirmed...

Infighting hinders progress

6 hours ago | Columns

Our traditional leaders, with all due respect, have been hogging the headlines for some time now, and mostly for the wrong reasons. Unnecessary infighting among...

Companies fail on health, safety

6 hours ago | Health

The majority of companies inspected by the labour ministry in the first quarter of this year were not in compliance with occupational health and safety...

Namibians dread worsening droughts

6 hours ago | Disasters

While Namibia is battling one of its worst droughts in history a mere 38% of Namibians say that droughts in the country have not become...

Olufuko launched tomorrow

6 hours ago | Cultural

The Olufuko Annual Cultural Festival has attracted 69 girls who have already registered with the organising committee to undergo initiation during this year's festival.The 2019...

Bolster fight against hepatitis E

6 hours ago | Health

The World Health Organisation (WHO) has again urged Namibia to boost its response to the protracted hepatitis E outbreak which has claimed the lives of...

NEPC financial woes due to...

6 hours ago | Government

Cash-strapped state-owned New Era Publications Corporation (NEPC)'s acting CEO Benjamin Jakobs has attributed the corporation's failure to account for N$33.5 million to employees' poor work...

Okapale komatukodhila taka lukilwa Ya...

6 hours ago | Transport

Otaku ka tulwa oshihongwathano shomukondjelimanguluko gwaNamibia, Herman Andimba Toivo Ya Toivo pokapale koondhila kaNdangwa.Shoka otashi ka ningwa nale nehangano lyoNamibia Airports Company (NAC) otali...

Pedalling buzz

6 hours ago | Sports

At least 100 cyclists are expected to take part in the first-ever Oshana Cycle Challenge, which will take place on Saturday. The first-of-its-kind challenge will...

Load More