Millions spent on unfinished govt office

20 June 2019 | Infrastructure

A N$16 million fisheries ministry infrastructure project in Rundu, which has been under construction since 2012, is still standing incomplete, resulting in officials operating from dilapidated rented offices.

According to the ministry the Kavango East regional office project has stalled because the contractor, Africa Civil Engineering, which was handed the site on 7 August 2015 to complete remaining work, has decided to inflate the price, which the ministry is not prepared to tolerate.

The works ministry is currently in the process of terminating the contract for this reason.

Executive City Construction was the initial contractor in 2012, until their contract was terminated for failing to carryout and complete the work as per the original scope.

“The project has gone for determination of contract, hence is not complete due to the price escalation, which is not permitted. Therefore the Ministry of Works and Transport is determining the contract of the contractor,” the fisheries ministry said in its response when contacted for comment.

It was reported in May last year that Africa Civil Engineering would complete the project by the end of 2018.

At the time Africa Civil Engineering's Petrus Kapula was quoted by New Era saying they have demonstrated their capacity to complete the project.

“We have demonstrated our capacity and capability to the ministry to conclude this project. Once everything and all agreements are in place, we will probably finish this project within six to seven months,” Kapula said.

It was further revealed that Africa Civil Engineering was paid about N$5.8 million for work done from 7 August 2015 to 7 July 2017.

About N$643 000 was retained by the works ministry, which was to be paid once the project was completed. Attempts to get comment from Kapula since last Friday proved futile as he was unreachable on his cellphone.

Africa Civil Engineering is currently constructing the N$7 million Kavango East Swapo office at Rundu, which has been delayed and was expected to be completed by April this year.

Namibian Sun visited fisheries office site and was greeted by a security guard, who was guarding the incomplete structures.

This was followed up by a visit to the Namibia Industrial Development Agency (NIDA) offices, formerly known as Namibia Development Corporation (NDC), where the ministry has been renting 13 offices and two storerooms for its officials for more than a decade.

The officials expressed their dissatisfaction with their working environment, as some plug sockets and the lights are not working and space is limited.

“As you can see the lights are not working and this is not my office; I just moved in here because in my office the plug is not functioning for me to connect my computer,” one official said on condition of anonymity.

“We are not informed about the incomplete office you are enquiring about, but all I can say is that we cannot carry out our work effectively.”

The ministry explained they are faced with a number of challenges at the rented premises.

“The Ministry of Fisheries and Marine Resources is currently renting offices from the NDC in Rundu for the 17 staff members of the DoAIF (directorate of aquaculture and inland fisheries) and operations. These offices do not have lab facilities for research and ponds for demonstration. Also lacking is a proper internet and telephone system,” ministry deputy director Elizabeth Swartz said. Swartz said the Kamutjonga Inland Fisheries Institute at Divundu is currently performing the research and demonstration function in Kavango East. Namibian Sun understands that once the office project is complete it will house an office building, ablution block, workshop, wash bay and net drying facility, a fish feed store, a boat, a trailer storage facility, garages, a generator room and a guard house.

The regional office will also offer installations of specialist services, equipment and associated ancillary site work.

KENYA KAMBOWE

Similar News

 

NHE loses N$10m in rental incompetence

2 weeks ago - 19 November 2019 | Infrastructure

A senior manager at the National Housing Enterprise, Willem Titus, is accused of failing to issue invoices for the sale of several houses at Ongwediva,...

WBCG grows regional economies

2 weeks ago - 19 November 2019 | Infrastructure

CATHERINE SASMANSince the establishment of the Walvis Bay Corridor Group (WBCG) 19 years ago, trade volumes from neighbouring countries have grown from zero to more...

TransNamib a mono oobiliyona 2.5

1 month - 15 October 2019 | Infrastructure

Omunambelewa omukomeho gwoTransNamib, Johny Smith okwa popi kutya oombaanga dhaNamiba oshowo ombaanga dhomuumbugantu waAfrica odha gandja ezimino lyoshimaliwa shoobiliyona 2.5 kehangano ndyoka lya yama...

A place to call home

2 months ago - 18 September 2019 | Infrastructure

Low-income residents in Oshakati and Okahao are paving the way to becoming homeowners as part of an innovative low-cost housing project.At Okahao, more than N$1.2...

Billions for new power lines

3 months ago - 29 August 2019 | Infrastructure

As part of its new strategic plan, NamPower is expected to spend upward of N$1 billion on the construction of three new heavy-current power lines...

Logistics vision gathers steam

3 months ago - 27 August 2019 | Infrastructure

Recent upgrades to Namibia's roads, railways and ports have brought the country closer to reaching logistical and economic targets.According to the Walvis Bay Corridor Group...

Fire kills one, destroys vessel

3 months ago - 19 August 2019 | Infrastructure

A man was killed when the hake trawler Ocean Tide moored at the jetty of Seawork Fish Processors in Walvis Bay caught fire below deck...

Bypass cuts deep

3 months ago - 19 August 2019 | Infrastructure

Residents of Vergenoeg, an 'illegal' settlement on the western outskirts of Okahandja, held a community meeting on Saturday afternoon. The purpose was to discuss the...

Air Nam flight delays due to grounded pilots

3 months ago - 16 August 2019 | Infrastructure

Complaints are flooding in from frustrated Air Namibia customers who say they had to spend hours at Hosea Kutako International Airport (HKIA) because of delayed...

Millions for Windhoek’s informal settlements

3 months ago - 15 August 2019 | Infrastructure

The ministry of urban and rural development has set aside N$50 million to improve the living conditions of Windhoek’s informal settlements residents for the 10...

Latest News

Creating a digital mindset for...

1 day - 06 December 2019 | Opinion

Jason AverbookDo you ever look back on your New Year’s resolutions (if you make them)? Do you even remember what they were? Maybe you resolve...

Article 47 bites back at...

1 day - 06 December 2019 | Politics

The Electoral Commission of Namibia (ECN) has approached attorney-general Albert Kawana for legal advice on how to deal with the situation arising from its enforcement...

Retrenched fishermen narrate ordeal

1 day - 06 December 2019 | Fishing

“My car was repossessed by the bank as I could no longer honour my payment obligations,” Sylvester Mbadi, a former employee of Namsov, has told...

Economic misery fuels suicides

1 day - 06 December 2019 | Health

Close to 400 people died by suicide between January and September 2019 and experts warn that Namibia's economic crisis, lack of jobs and the crippling...

Highly mechanised

1 day - 06 December 2019 | People

Justicia Shipena Vivacious Marco Swart is a mechanical technician in the packaging engineering department at Namibia Breweries Limited (NBL) - a subsidiary of the Ohlthaver...

Compassion is the new fashion

1 day - 06 December 2019 | People

Evany van WykMarizelle Pienaar lives by the motto, “the more you have to do, the more you get done.” She believes in being a balanced...

Never say never

1 day - 06 December 2019 | People

Mariselle StofbergHester Uushona is a firm believer that being average in life is not an option. She strives towards making her mark while providing others...

Not all with be festive

1 day - 06 December 2019 | Columns

As the festive season approaches in full-force, many are yearning to spend time with their loved ones away from the stress work and the accompanying...

Talent knows no borders

1 day - 06 December 2019 | Cultural

Ester Kamati Still digesting the news after receiving his award on 30 November in Burkina Faso, Visagie is passionate about ensuring that the arts are...

Load More