Unfinished pipeline impacts 7 000 residents

20 March 2019 | Infrastructure

About 6 932 people and 33 790 large and 18 395 small stock units are facing thirst, as the agriculture ministry battles to finish the Ondangwa-Omuntele pipeline project.

The initial budget for the project was N$46.4 million in 2014, but it ballooned to N$51.1 million in 2017. In March 2017 the contractor stopped working with only 89% of the work complete.

The water ministry terminated the contract and is currently considering an official procurement process for the construction work to resume in the 2019/20 financial year. This is according to agriculture ministry executive director Percy Misika. Misika said the pipeline extension scheme stretches for about 50 kilometres in a south-western direction to Onadhi and eastwards to Onanke and is expected to benefit more than 928 households, constituting 6 932 direct beneficiaries and 33 790 large and 18 395 small stock units.

“The initial budget of the project contract in 2014 was N$46 374 883, but by 2017 the estimated contract value was N$51 116 368. During the construction stage a six-month extension of time was approved for the contractor, based on certain challenges that were experienced by the contractor as well as the ministry.

“Within the granted extension time period the contractor terminated the contract due to extreme cash flow problems caused by late payments,” Misika said in the response to enquiries by Namibian Sun. “The six months lapsed on 31 March 2017; the construction work was therefore not finalised and the contractor stopped all work on-site. The prolonging of the completion of the construction and additional work caused additional costs that exceeded the contract amount.” The Omuntele constituency councillor Sacky Nangula said the pipeline project initially was planned from Omuntele to Onadhi, but was extended by 20 kilometres to Okuma. The budget thus proved insufficient.

Misika added that another challenge that emerged was the bulk water supply by NamWater.

He said due to the considerable increase in water demand on the current infrastructure, additional upgrades of existing infrastructure is envisaged this will contribute to additional costs for the Ondangwa-Omuntele extension scheme.

He said the project was initiated as a drought relief scheme, due to poor groundwater quality (saline and brackish) and the quantity of water in the region.

He said it was found that various parts of northern Namibia are well-known for poor water quality and in certain circumstances the quantity of available water is also problematic.

Government and the relevant authorities had to take action to provide potable water for both the residents and livestock in these parts of the country.

“Due to fact that the original contract was terminated, an official procurement process in line with the Public Procurement Act will have to be started in the 2019/20 financial year. Budget provision is already made for the completion of the scheme.

“The construction of the Ondangwa-Omuntele extension (original contract) is 89% complete. The main outstanding items are special fittings (air valves, scour valves, bulk water meters), a booster pump station in Omuntele, final work at the reservoir in Omuntele, elephant protection measures at some of the water points in the grazing area, and testing and commissioning,” Misika added.

ILENI NANDJATO

Similar News

 

AR’s Goreangab plots still being serviced five years later

1 week ago - 28 July 2020 | Infrastructure

OGONE TLHAGEWINDHOEKLand that the Affirmative Repositioning movement proposed for mass housing in Windhoek’s Goreangab informal settlement as part of a deal struck with State House...

War vets furious over housing 'propaganda'

3 weeks ago - 15 July 2020 | Infrastructure

ILENI NANDJATOONESIPeople's Liberation Army of Namibia (PLAN) pioneer war veterans - most of whom are still living in poverty and squalor - say they are...

Harambee target still unachieved

1 month - 09 June 2020 | Infrastructure

KENYA KAMBOWERUNDUPresident Hage Geingob's administration has not yet attained the goal of water security outlined by the Harambee Prosperity Plan (HPP) - a national plan...

Massive capital projects delayed

2 months ago - 05 June 2020 | Infrastructure

Phillepus UusikuThe arrival of Covid-19 has had far-reaching consequences on Namibia, with major road-building projects delayed in the Windhoek area.There are three ongoing projects in...

Congested roads expected

3 months ago - 07 May 2020 | Infrastructure

ELLANIE SMIT WINDHOEK With the national lockdown officially being lifted, thousands of Namibians are expected to start travelling again, causing major...

'Land or death'

3 months ago - 06 May 2020 | Infrastructure

Kenya KamboweRUNDUAt Rundu's Sauyemwa Extension 1, squatters are demanding that the local authority provide them with land.They further said the town council must “forget” about...

Coronavirus silver lining for Walvis port

3 months ago - 05 May 2020 | Infrastructure

JEMIMA BEUKESWINDHOEKThe coronavirus-inspired lockdown in South Africa is credited in part with increased cargo at the port of Walvis Bay, which has become preferred...

NHE offers 3 months payment relief

4 months ago - 06 April 2020 | Infrastructure

NAMPAGOBABIS As part of its response to the challenges posed by the coronavirus, the National Housing Enterprise (NHE) has offered payment relief to its...

Increased access to water and sanitation

4 months ago - 25 March 2020 | Infrastructure

ELLANIE SMIT A total of 7 684 boreholes have been drilled and fitted since independence and 51 water supply schemes have...

Water governance outdated

4 months ago - 23 March 2020 | Infrastructure

ELLANIE SMIT WINDHOEKThere is an urgent need for a legally binding water regulatory framework, therefore government should enforce the Water Resource Management Act of 2013.This...

Latest News

Border bribery syndicate exposed

5 hours ago | Crime

OGONE TLHAGE WINDHOEK Namibian authorities have widened their investigation into the case of Immanuel David, who allegedly paid bribes to various individuals so...

Shame on Namibian football ‘gods’

5 hours ago | Opinion

Like the body of a disgraced African dictator awaiting official communication on what is to be done with it, Namibian football has been lying in...

Fishrot's De Klerk washes dirty...

5 hours ago | Justice

RONELLE RADEMEYER WINDHOEK Marén de Klerk, the lawyer who left Namibia amid allegations that millions of dollars from the Fishrot bribery scandal had passed...

She’s got style

5 hours ago | Art and Entertainment

MICHAEL KAYUNDE WINDHOEK Launched in 2018, stylist Yverischka Ivertor Bok is happy with the pace at which her brand,...

10th NAMAs go virtual

5 hours ago | Art and Entertainment

STAFF REPORTER WINDHOEK The Namibian Annual Music Awards executive committee recently announced that the 10th NAMAs will be delivered online. The event will...

Keeping it real

5 hours ago | Art and Entertainment

Awards season is finally in full swing, and this is testament to the stories carried in this edition.After being in suspense for a few months,...

Boy accused of murder granted...

5 hours ago | Justice

NAMPAGOBABISA 14-year-old boy who allegedly stabbed an 18-year-old to death at the Kanaan A informal settlement in Gobabis this past Saturday has been granted bail...

Pangolin traffickers nabbed

5 hours ago | Crime

ELLANIE SMITWINDHOEKIn the first cooperation between US law enforcement and the Namibian police, four suspected pangolin traffickers were recently arrested in Namibia.According to a statement...

Germany should fund Namibia's land...

5 hours ago | Columns

Henning Melber Nearly 30 years after starting land reform, Namibia's distribution of land ownership is still skewed. This is a colonial legacy. It is high...

Load More