Road works well on target – RA

The Roads Authority says all construction projects are continuing without major hurdles.

03 February 2017 | Infrastructure

CATHERINE SASMAN



The Roads Authority (RA) has pointedly denied any recent work stoppages on any of the major road construction projects.

RA chief executive officer Conrad Lutombi also insists that there is sufficient budgetary provision to complete on schedule multibillion-dollar projects.

This is despite numerous phone calls from role players who have complained about non-payment and resultant delays in the resumption of work after the builders’ holiday between 15 December and 15 January.

Callers claimed that work on the N$1.085 billion second phase of the dual carriageway between Windhoek and Okahandja had started later than scheduled because of outstanding payments. The road is being built by the Namibian outfit Otesa Civil Engineering and Italian company CMC Ravenna.

Not so, said Lutombi.

“The fact of the matter is that this is a government project. There is no history in Namibia since independence where the government undertook a project and just abandoned it, especially a critical project such as [the Windhoek to] Okahandja road,” he said.

“What is happening is operational matters and those are being handled within the parameters of the project.”

Otesa director Elmo Kaiyamo was equally adamant that there has never been any work stoppage on this project. He said work continued until 16 December and resumed in January.

Kaiyamo said work picked up slowly in January because a huge value chain took time to mobilise.

DR3609

There were also complaints of an alleged downscaling of work due to non-payment since June/July on the DR3609 road from Oshakati to Omungwelune and Ongenga, which reportedly forced a reduction of 145 to 15 workers.

This 37-kilometre road is being built by the Chinese firm Zhong Mei Engineering at a cost of N$216 million. Lutombi acknowledged that a N$46 million payment was due on 19 January but he was adamant that the invoicing was being processed and payment was about to be made.

Lutombi said because work on this project was already 95% complete it was less labour-intensive than at the start when earthworks and de-bushing had to be done.

He acknowledged some delays but said these were due to protracted and complex negotiations with villagers along the route.

Lutombi said contractors were entitled to stop work should there be undue late payments. Contractually the RA must pay contractors within 56 days after they have submitted interim payment certificates.

Should a payment not be made, the contractor must give 21 days’ notice of a planned work stoppage.

UNAUTHORISED, UNBUDGETED PROJECTS

Sources maintain that payments have been sluggish because the RA has “overcommitted” on projects on behalf of the government because of a lack of proper management and planning.

“No project should be committed without the assurance of finance,” one source said. “Right now the RA finds itself with many debts which the CEO [Lutombi] openly denies.”

Finance minister Calle Schlettwein last week stated that some major road projects – including the more than N$1 billion second phase of the Windhoek to Okahandja road, the N$900 million first phase of the Windhoek to Hosea Kutako International Airport dual carriageway, as well as the yet-to-be-designed Uis to Khorixas-Kamanjab road – had not been budgeted for or authorised.

The RA’s commitment to such projects has forced the government’s hand to free some N$450 million from the Road Fund Administration (RFA) despite the fact that there was no such provision in the RFA’s five-year business plan for the period April 2017 to March 2022.

The business plan only makes provision for new developments, rehabilitation and maintenance. However, as far as Lutombi is concerned the RFA was supposed to make provision for “economic roads” as well.

“The only reason why the RFA is only covering maintenance is because the collection of revenue is not much,” he said.

Schlettwein issued a stern warning that he would invoke Section 17 of the Finance Act - in other words that the state would not pay for any further unauthorised expenditure.

According to Lutombi, however, the RA has made budgetary provision “under the RFA budget”.

“As far as this financial year [which ends on 31 March] is concerned we have no problem; the work will continue until April. The critical one is whether we have funding for the next financial year and we do have that funding. We have budgeted under RFA funding for the next financial year moving forward,” Lutombi said.

Similar News

 

Africa road conference in July

11 hours ago | Infrastructure

The second International Road Federation (IRF) Africa Regional Congress will be hosted next month in Windhoek. The conference, which will be hosted in collaboration with...

RCC liquidation about 'egos'

1 week ago - 20 June 2017 | Infrastructure

Roads Contractor Company (RCC) chairman Fritz Jacobs has described calls to liquidate the embattled parastatal as “egotistical” and says it is not necessary given his...

Oshikumungu shoFarm 37 sha yelekwa

1 week ago - 19 June 2017 | Infrastructure

OTIS FINCKAakwashigwana oya popi kutya konima sho a tseyitilwa kutya oNamibia Planning Advisory Board (NAMPAB) oya zimina opo ofaalama ndjoka yi pewe po elelo lyondoolopa...

Walvis expands rapidly

1 week ago - 16 June 2017 | Infrastructure

The municipality Walvis Bay approved and recorded building plans with a total value of N$828.7 million between November 2015 and February 2017. “The value...

N$36m road that never was

1 week ago - 15 June 2017 | Infrastructure

The Roads Authority and the Roads Contractor Company are failing to explain why the construction of the N$36 million 40km gravel road between Omakange and...

N$12b transport plan under fire

3 weeks ago - 07 June 2017 | Infrastructure

A number of concerns were raised this week during the final presentation of the much-anticipated transport masterplan for the four northern regions, including fears that...

Etungo lyOombonge dhOpolisi moMusati inali manithwa natango

3 weeks ago - 05 June 2017 | Infrastructure

Omatungo ngoka monena otaga gu opainda niilongitho natango oya halakana owala pehala ndyoka, pethimbo oshifokundaneki shoNamibian Sun sha talele po ehala ndyoka, na kaku shiwike...

House prices still on the up

3 weeks ago - 01 June 2017 | Infrastructure

FNB Namibia has released the latest residential property index and Josephat Nambashu, an analyst at FNB Namibia, advised that median property prices rose by 13.3%...

Banks must help with housing

1 month - 22 May 2017 | Infrastructure

The Minister of Urban and Rural Development, Sophia Shaningwa, has called on banks to meet the government halfway in its efforts to provide affordable housing...

Vet foreign engineers

1 month - 10 May 2017 | Infrastructure

The Namibian Society of Engineers has called on the Ministry of Home Affairs and Immigration to carry out due-diligence in the issuance of work permits...

Latest News

Domestic workers and employers should...

11 hours ago | Labour

The Namibia Domestic and Allied Workers’ Union (Ndawu) has urged domestic workers and their employers to work together for a conducive work environment, where the...

Africa road conference in July

11 hours ago | Infrastructure

The second International Road Federation (IRF) Africa Regional Congress will be hosted next month in Windhoek. The conference, which will be hosted in collaboration with...

N$2.5 mill cigarette fraud case...

11 hours ago | Crime

The fraud case against former employees of the then Indo Atlantic, now Commercial Investment Corporation (CIC) at Walvis Bay, which is on-going for over six...

Venaani urged to toe the...

11 hours ago | Politics

The minister in the presidency, Frans Kapofi has vehemently come out in defence of his boss, President Hage Geingob who swore that 'heads would roll',...

Still dependent on export markets

11 hours ago | Business

Namibia is likely to remain dependent on export markets for beef, while it is unlikely that the local market will become a high-value earner for...

When we forget who voted

11 hours ago | Opinion

In the Hardap Region of Namibia, it is alleged that the governor used vulgar language and made some dangerously insulting tribal inferences at members of...

Shot of the day

11 hours ago | Picture of the day

WAITING: A fan waits for the start of the 2017 Confederations Cup group B football match between Australia and Germany at the Fisht Stadium in...

Namibia bans poultry imports

11 hours ago | Agriculture

Namibia has suspended the import and in transit movement of live poultry, birds and products from South Africa and Belgium following the outbreak of bird...

Landowners submit appeals against land...

11 hours ago | Agriculture

The appeal of more than 300 landowners against last year's verdict by the Valuation Court has been submitted to the High Court. According to the...

Load More