Road works well on target – RA

The Roads Authority says all construction projects are continuing without major hurdles.

03 February 2017 | Infrastructure

CATHERINE SASMAN



The Roads Authority (RA) has pointedly denied any recent work stoppages on any of the major road construction projects.

RA chief executive officer Conrad Lutombi also insists that there is sufficient budgetary provision to complete on schedule multibillion-dollar projects.

This is despite numerous phone calls from role players who have complained about non-payment and resultant delays in the resumption of work after the builders’ holiday between 15 December and 15 January.

Callers claimed that work on the N$1.085 billion second phase of the dual carriageway between Windhoek and Okahandja had started later than scheduled because of outstanding payments. The road is being built by the Namibian outfit Otesa Civil Engineering and Italian company CMC Ravenna.

Not so, said Lutombi.

“The fact of the matter is that this is a government project. There is no history in Namibia since independence where the government undertook a project and just abandoned it, especially a critical project such as [the Windhoek to] Okahandja road,” he said.

“What is happening is operational matters and those are being handled within the parameters of the project.”

Otesa director Elmo Kaiyamo was equally adamant that there has never been any work stoppage on this project. He said work continued until 16 December and resumed in January.

Kaiyamo said work picked up slowly in January because a huge value chain took time to mobilise.

DR3609

There were also complaints of an alleged downscaling of work due to non-payment since June/July on the DR3609 road from Oshakati to Omungwelune and Ongenga, which reportedly forced a reduction of 145 to 15 workers.

This 37-kilometre road is being built by the Chinese firm Zhong Mei Engineering at a cost of N$216 million. Lutombi acknowledged that a N$46 million payment was due on 19 January but he was adamant that the invoicing was being processed and payment was about to be made.

Lutombi said because work on this project was already 95% complete it was less labour-intensive than at the start when earthworks and de-bushing had to be done.

He acknowledged some delays but said these were due to protracted and complex negotiations with villagers along the route.

Lutombi said contractors were entitled to stop work should there be undue late payments. Contractually the RA must pay contractors within 56 days after they have submitted interim payment certificates.

Should a payment not be made, the contractor must give 21 days’ notice of a planned work stoppage.

UNAUTHORISED, UNBUDGETED PROJECTS

Sources maintain that payments have been sluggish because the RA has “overcommitted” on projects on behalf of the government because of a lack of proper management and planning.

“No project should be committed without the assurance of finance,” one source said. “Right now the RA finds itself with many debts which the CEO [Lutombi] openly denies.”

Finance minister Calle Schlettwein last week stated that some major road projects – including the more than N$1 billion second phase of the Windhoek to Okahandja road, the N$900 million first phase of the Windhoek to Hosea Kutako International Airport dual carriageway, as well as the yet-to-be-designed Uis to Khorixas-Kamanjab road – had not been budgeted for or authorised.

The RA’s commitment to such projects has forced the government’s hand to free some N$450 million from the Road Fund Administration (RFA) despite the fact that there was no such provision in the RFA’s five-year business plan for the period April 2017 to March 2022.

The business plan only makes provision for new developments, rehabilitation and maintenance. However, as far as Lutombi is concerned the RFA was supposed to make provision for “economic roads” as well.

“The only reason why the RFA is only covering maintenance is because the collection of revenue is not much,” he said.

Schlettwein issued a stern warning that he would invoke Section 17 of the Finance Act - in other words that the state would not pay for any further unauthorised expenditure.

According to Lutombi, however, the RA has made budgetary provision “under the RFA budget”.

“As far as this financial year [which ends on 31 March] is concerned we have no problem; the work will continue until April. The critical one is whether we have funding for the next financial year and we do have that funding. We have budgeted under RFA funding for the next financial year moving forward,” Lutombi said.

Similar News

 

Fast-track land servicing: Shaningwa

4 days ago - 20 February 2017 | Infrastructure

The minister of urban and rural development, Sophia Shaningwa, has urged her staff to explore all options at their disposal to fast-track land servicing in...

Walvis landless are hopeful

1 week ago - 16 February 2017 | Infrastructure

News that land could be made available at Farm 37 near Walvis Bay for housing was met with applause and ululation at a meeting on...

Road works well on target – RA

3 weeks ago - 03 February 2017 | Infrastructure

CATHERINE SASMAN The Roads Authority (RA) has pointedly denied any recent work stoppages on any of the major road construction...

Packed classrooms hamper learning

3 weeks ago - 03 February 2017 | Infrastructure

The completion of several crucial capital projects is being hampered by the country's financial problems.Agriculture minister John Mutorwa said during his annual policy statement that...

1 000 Walvis homes by June

3 weeks ago - 31 January 2017 | Infrastructure

Urban and rural development minister Sophia Shaningwa has expressed satisfaction with the prices and quality of show houses being built by 22 contractors in Walvis...

Electrification starts at Ekuku

3 weeks ago - 31 January 2017 | Infrastructure

The latest phase of the mass land servicing project at Ekuku township in Oshakati is the electrification process, which will cost the council N$21 million....

Work on Windhoek-Okahandja road stops

1 month - 17 January 2017 | Infrastructure

Conflicting reports have emerged on whether work has stopped on the N$1.085 billion second phase of the dual carriageway between Windhoek and Okahandja.According to some...

Mariental houses handed over

2 months ago - 16 December 2016 | Infrastructure

The government has committed itself to providing housing that is not only decent, but also affordable.This was said by the minister of urban and rural...

Staff rewarded with their own home

2 months ago - 15 December 2016 | Infrastructure

Friday 2 December marked a historic occasion in Namibia. That day, the Rock Village, a residential complex in Okahandja, was officially opened by the Speaker...

Rude drivers delay fire brigade

2 months ago - 08 December 2016 | Infrastructure

The Otjiwarongo Municipality has entered into a land servicing deal with UUM Investment under a public private partnership (PPP) to service Extension 8 and 10.Minister...

Latest News

Robber assaults sleeping baby

19 hours ago | Crime

JESSICA BOTES A Swakopmund mother of twin babies is the latest victim of a string of violent burglaries in Swakopmund.At approximately 03:50 on Wednesday, a...

Rosh Pinah Zinc workers want...

19 hours ago | Labour

Workers at the Rosh Pinah Zinc Mine have given management four working days to remove its employee relations specialist, Angeline Barnard-Hagen, or face “unforeseen action”.In...

Land activists say they won't...

19 hours ago | Politics

The Landless People's Movement has indicated its intention to approach the ombudsman to compel the land reform ministry to release its version of the resettlement...

Union wants non-compliant retailers to...

19 hours ago | Labour

The Namibia Wholesale and Retail Workers Union (NWRWU) has demanded that the minister of labour call retailers that exploit workers to order. The union claims...

Hoff guilty of attempted murder...

19 hours ago | Crime

Susanne Hoff (56) was found guilty of the attempted murder of her estranged husband, Egbert Hoff, by the Windhoek Regional Court yesterday.Hoff, who pleaded not...

Ondonga backs Nangolo to succeed...

19 hours ago | Cultural

The Ondonga Traditional Authority on Tuesday affirmed that Fillemon Shuumbwa Nangolo is the Ondonga king-in-waiting.The OTA said in a statement that King Immanuel Kauluma Elifas...

Dineo storms onto bucket list

19 hours ago | Disasters

When you plan a sunny Mozambican holiday in February, the last thing you expect is to be caught up in a cyclone. (Well, maybe we...

The 2017 Budget should demonstrate...

19 hours ago | Opinion

BY MALLY LIKUKELA As preparations for the 2017 National Budget gather momentum and a greater participation by various stakeholders becomes evident. The budget is...

I am a foolishly wise...

19 hours ago | Opinion

I have always been fascinated by the manner in which the Police in United States of America, in cities like New York, Los Angeles or...

Load More