Road works well on target – RA

The Roads Authority says all construction projects are continuing without major hurdles.

03 February 2017 | Infrastructure

CATHERINE SASMAN



The Roads Authority (RA) has pointedly denied any recent work stoppages on any of the major road construction projects.

RA chief executive officer Conrad Lutombi also insists that there is sufficient budgetary provision to complete on schedule multibillion-dollar projects.

This is despite numerous phone calls from role players who have complained about non-payment and resultant delays in the resumption of work after the builders’ holiday between 15 December and 15 January.

Callers claimed that work on the N$1.085 billion second phase of the dual carriageway between Windhoek and Okahandja had started later than scheduled because of outstanding payments. The road is being built by the Namibian outfit Otesa Civil Engineering and Italian company CMC Ravenna.

Not so, said Lutombi.

“The fact of the matter is that this is a government project. There is no history in Namibia since independence where the government undertook a project and just abandoned it, especially a critical project such as [the Windhoek to] Okahandja road,” he said.

“What is happening is operational matters and those are being handled within the parameters of the project.”

Otesa director Elmo Kaiyamo was equally adamant that there has never been any work stoppage on this project. He said work continued until 16 December and resumed in January.

Kaiyamo said work picked up slowly in January because a huge value chain took time to mobilise.

DR3609

There were also complaints of an alleged downscaling of work due to non-payment since June/July on the DR3609 road from Oshakati to Omungwelune and Ongenga, which reportedly forced a reduction of 145 to 15 workers.

This 37-kilometre road is being built by the Chinese firm Zhong Mei Engineering at a cost of N$216 million. Lutombi acknowledged that a N$46 million payment was due on 19 January but he was adamant that the invoicing was being processed and payment was about to be made.

Lutombi said because work on this project was already 95% complete it was less labour-intensive than at the start when earthworks and de-bushing had to be done.

He acknowledged some delays but said these were due to protracted and complex negotiations with villagers along the route.

Lutombi said contractors were entitled to stop work should there be undue late payments. Contractually the RA must pay contractors within 56 days after they have submitted interim payment certificates.

Should a payment not be made, the contractor must give 21 days’ notice of a planned work stoppage.

UNAUTHORISED, UNBUDGETED PROJECTS

Sources maintain that payments have been sluggish because the RA has “overcommitted” on projects on behalf of the government because of a lack of proper management and planning.

“No project should be committed without the assurance of finance,” one source said. “Right now the RA finds itself with many debts which the CEO [Lutombi] openly denies.”

Finance minister Calle Schlettwein last week stated that some major road projects – including the more than N$1 billion second phase of the Windhoek to Okahandja road, the N$900 million first phase of the Windhoek to Hosea Kutako International Airport dual carriageway, as well as the yet-to-be-designed Uis to Khorixas-Kamanjab road – had not been budgeted for or authorised.

The RA’s commitment to such projects has forced the government’s hand to free some N$450 million from the Road Fund Administration (RFA) despite the fact that there was no such provision in the RFA’s five-year business plan for the period April 2017 to March 2022.

The business plan only makes provision for new developments, rehabilitation and maintenance. However, as far as Lutombi is concerned the RFA was supposed to make provision for “economic roads” as well.

“The only reason why the RFA is only covering maintenance is because the collection of revenue is not much,” he said.

Schlettwein issued a stern warning that he would invoke Section 17 of the Finance Act - in other words that the state would not pay for any further unauthorised expenditure.

According to Lutombi, however, the RA has made budgetary provision “under the RFA budget”.

“As far as this financial year [which ends on 31 March] is concerned we have no problem; the work will continue until April. The critical one is whether we have funding for the next financial year and we do have that funding. We have budgeted under RFA funding for the next financial year moving forward,” Lutombi said.

Similar News

 

NDP5 taken to Hardap

2 weeks ago - 31 July 2017 | Infrastructure

The deputy minister of economic planning, Lucia Iipumbu last week visited Mariental in the Hardap Region as part of the National Planning Commission's (NPC) popularisation...

Hardap alleviates Neckartal water woes

3 weeks ago - 25 July 2017 | Infrastructure

STAFF REPORTERNamWater will funnel crucial water from the Hardap Dam to the Neckartal Dam construction site in order to alleviate critical water shortages there and...

Desert Rose EIA under scrutiny

3 weeks ago - 25 July 2017 | Infrastructure

The developers of the Desert Rose project are keen to get the project rolling, having recently submitted an environmental impact assessment (EIA) for the N$8-billion...

Chinese firms stop work amid financial woes

3 weeks ago - 24 July 2017 | Infrastructure

Two Chinese companies responsible for the bulk earthworks for the construction of the railway line between Ondangwa and Oshakati have reportedly stopped work due to...

Dunes Mall nearly done

3 weeks ago - 21 July 2017 | Infrastructure

The construction of the Dunes Mall with an estimated value of N$650 million in the vicinity of the Diaz Circle in Walvis Bay is on...

Millions for new port gate

3 weeks ago - 21 July 2017 | Infrastructure

Namport intends to start with the construction of a new port entrance gate and truck staging area at a cost of approximately N$40 million in...

Housing remains priority

4 weeks ago - 19 July 2017 | Infrastructure

The City of Windhoek aims to provide 4 043 affordable houses in the next five years through projects such as National Mass Housing and the...

Oobiliyona tadhi ka longithwa mokutunga omagumbo

1 month - 14 July 2017 | Infrastructure

Oshimaliwa sha thika poobiliyona 1.4 otashi ka longithwa mokutunga omagumbo ngoka oshowo okuyambulapo onkalo yomagumbo galwe nonkalo yoluhepo mokati kaakwashigwana yaNamibia otayi ka shuna...

Onguta becomes township

1 month - 06 July 2017 | Infrastructure

The town council of Ondangwa is in the process of formalising one of its oldest locations Onguta.According to the town's technical manager, Petrus Shipanga, the...

Omaruru savings scheme starts constructing houses

1 month - 29 June 2017 | Infrastructure

'River C', a Shack Dwellers Federation housing scheme in Omaruru, this weekend commenced with the construction of 26 houses after years of technical and natural...

Latest News

Local women in jails abroad

16 hours ago | Crime

In the last year Namibians have made headlines for being arrested in foreign countries for carrying drugs or for other crimes.Security experts are of the...

Security guard caught with N$500...

16 hours ago | Crime

A security guard was arrested at Otjiwarongo yesterday in connection with the theft of about half a million dollars in cash that had been collected...

Yemeni denies guilt in murder...

16 hours ago | Justice

A Yemeni man arrested for the alleged murder of a Malian national in Windhoek in August 2016 yesterday denied committing the offence.Murad Esmail Ali Al-Hersh,...

Tourists' road safety a concern

16 hours ago | Accidents

With at least eight tourists having been killed on Namibia's roads in separate accidents during the last three weeks, the safety of the country's roads...

I'm no snitch – Swartbooi

16 hours ago | Politics

Former deputy lands minister Bernadus Swartbooi has told people who are holding their breaths for him to expose corrupt Swapo politicians that he has no...

Opposition to communication gateway

16 hours ago | Politics

The DTA has joined the Namibia Media Trust in condemning an alleged intended move by information and communication technology minister Tjekero Tweya to select a...

PAAB files with court

16 hours ago | Crime

The Public Accountants' and Auditors' Board (PAAB) last Thursday, filed its record of proceedings with the High Court in its defence against auditor Hans Hashagen's...

Swapo members claim Mbumba let...

16 hours ago | Politics

Swapo secretary-general Nangolo Mbumba says he will only meet with the party members in Rehoboth when the “time is right”. His remarks come after claims...

Clampdown on wildlife crime

16 hours ago | Crime

An intelligence-led investigation conducted in the Kavango East Region last week recovered uncut diamonds, ivory and other wildlife products worth N$4 million and four suspects...

Load More