Road works well on target – RA

The Roads Authority says all construction projects are continuing without major hurdles.

03 February 2017 | Infrastructure

CATHERINE SASMAN



The Roads Authority (RA) has pointedly denied any recent work stoppages on any of the major road construction projects.

RA chief executive officer Conrad Lutombi also insists that there is sufficient budgetary provision to complete on schedule multibillion-dollar projects.

This is despite numerous phone calls from role players who have complained about non-payment and resultant delays in the resumption of work after the builders’ holiday between 15 December and 15 January.

Callers claimed that work on the N$1.085 billion second phase of the dual carriageway between Windhoek and Okahandja had started later than scheduled because of outstanding payments. The road is being built by the Namibian outfit Otesa Civil Engineering and Italian company CMC Ravenna.

Not so, said Lutombi.

“The fact of the matter is that this is a government project. There is no history in Namibia since independence where the government undertook a project and just abandoned it, especially a critical project such as [the Windhoek to] Okahandja road,” he said.

“What is happening is operational matters and those are being handled within the parameters of the project.”

Otesa director Elmo Kaiyamo was equally adamant that there has never been any work stoppage on this project. He said work continued until 16 December and resumed in January.

Kaiyamo said work picked up slowly in January because a huge value chain took time to mobilise.

DR3609

There were also complaints of an alleged downscaling of work due to non-payment since June/July on the DR3609 road from Oshakati to Omungwelune and Ongenga, which reportedly forced a reduction of 145 to 15 workers.

This 37-kilometre road is being built by the Chinese firm Zhong Mei Engineering at a cost of N$216 million. Lutombi acknowledged that a N$46 million payment was due on 19 January but he was adamant that the invoicing was being processed and payment was about to be made.

Lutombi said because work on this project was already 95% complete it was less labour-intensive than at the start when earthworks and de-bushing had to be done.

He acknowledged some delays but said these were due to protracted and complex negotiations with villagers along the route.

Lutombi said contractors were entitled to stop work should there be undue late payments. Contractually the RA must pay contractors within 56 days after they have submitted interim payment certificates.

Should a payment not be made, the contractor must give 21 days’ notice of a planned work stoppage.

UNAUTHORISED, UNBUDGETED PROJECTS

Sources maintain that payments have been sluggish because the RA has “overcommitted” on projects on behalf of the government because of a lack of proper management and planning.

“No project should be committed without the assurance of finance,” one source said. “Right now the RA finds itself with many debts which the CEO [Lutombi] openly denies.”

Finance minister Calle Schlettwein last week stated that some major road projects – including the more than N$1 billion second phase of the Windhoek to Okahandja road, the N$900 million first phase of the Windhoek to Hosea Kutako International Airport dual carriageway, as well as the yet-to-be-designed Uis to Khorixas-Kamanjab road – had not been budgeted for or authorised.

The RA’s commitment to such projects has forced the government’s hand to free some N$450 million from the Road Fund Administration (RFA) despite the fact that there was no such provision in the RFA’s five-year business plan for the period April 2017 to March 2022.

The business plan only makes provision for new developments, rehabilitation and maintenance. However, as far as Lutombi is concerned the RFA was supposed to make provision for “economic roads” as well.

“The only reason why the RFA is only covering maintenance is because the collection of revenue is not much,” he said.

Schlettwein issued a stern warning that he would invoke Section 17 of the Finance Act - in other words that the state would not pay for any further unauthorised expenditure.

According to Lutombi, however, the RA has made budgetary provision “under the RFA budget”.

“As far as this financial year [which ends on 31 March] is concerned we have no problem; the work will continue until April. The critical one is whether we have funding for the next financial year and we do have that funding. We have budgeted under RFA funding for the next financial year moving forward,” Lutombi said.

Similar News

 

Ehala lyomathikilo gokapale kaNdangwa otali tekapo

2 weeks ago - 28 September 2017 | Infrastructure

Ø ILENI NANDJATOMinista Calle Schlettwein okwa popi kutya nonando ehala ndyoka olya li lya longwa koshimaliwa shoomiliyona 84 konima owala yoomvula mbali dha piti,...

New homes for nurses at Nzinze

3 weeks ago - 22 September 2017 | Infrastructure

The American ambassador to Namibia, Thomas Daughton on Tuesday handed over a modular house valued at N$860 000 to the health ministry's Nzinze Clinic in...

No pay, no work, says Salini

4 weeks ago - 18 September 2017 | Infrastructure

The Neckartal Dam contractors will not resume construction activities until it is paid an overdue bill of N$600 million for work completed over the last...

PPP sought for Keetmans housing

1 month - 14 September 2017 | Infrastructure

In line with cost-cutting in tough economic times, the urban and rural development ministry, along with the Keetmanshoop Municipality, are looking into public-private partnerships to...

NHE fails to build houses

1 month - 13 September 2017 | Infrastructure

President Hage Geingob is accused of having “misled” the Namibian nation by claiming during his 2017 state of the nation address (SONA) that more than...

NHE boss sniffs at PPP model

1 month - 31 August 2017 | Infrastructure

National Housing Enterprise (NHE) chief executive officer Gisbertus Mukulu says as long as private developers service land and build houses, property prices will remain high.Talking...

NDP5 taken to Hardap

2 months ago - 31 July 2017 | Infrastructure

The deputy minister of economic planning, Lucia Iipumbu last week visited Mariental in the Hardap Region as part of the National Planning Commission's (NPC) popularisation...

Hardap alleviates Neckartal water woes

2 months ago - 25 July 2017 | Infrastructure

STAFF REPORTERNamWater will funnel crucial water from the Hardap Dam to the Neckartal Dam construction site in order to alleviate critical water shortages there and...

Desert Rose EIA under scrutiny

2 months ago - 25 July 2017 | Infrastructure

The developers of the Desert Rose project are keen to get the project rolling, having recently submitted an environmental impact assessment (EIA) for the N$8-billion...

Chinese firms stop work amid financial woes

2 months ago - 24 July 2017 | Infrastructure

Two Chinese companies responsible for the bulk earthworks for the construction of the railway line between Ondangwa and Oshakati have reportedly stopped work due to...

Latest News

Teachers' demo on for today

4 hours ago | Labour

Teachers are determined to stage protests today to express their frustration with the ministry's delay in publishing the vacancy bulletin for next year.This protest action...

NEFF blames councils for failed...

4 hours ago | Politics

ILENI NANDJATOThe Namibian Economic Freedom Fighters (NEFF) blame local authorities for the failure of their grandiose N$3 billion housing scheme.The party says local councils did...

Namibia's hunger pangs lessen

4 hours ago | Economics

Good progress has been made over the past 25 years to reduce Namibia's hunger levels by 27%, the Global Hunger Index shows.According to the latest...

New minimum wage for farmworkers

4 hours ago | Labour

The minimum wage for farmworkers has been increased by 25% and will come into force on 1 November this year. This follows successful negotiations...

Can Swapo heal itself?

4 hours ago | Politics

Political analysts are concerned that the once “mighty” Swapo may not make it in one piece through its highly anticipated elective congress next month. ...

Speaker seeks Finnish help in...

4 hours ago | Government

The Speaker of the National Assembly, Peter Katjavivi, is concerned about increasing cases of gender-based violence in Namibia and appealed to the Finnish political leadership...

Struggle vet seeks eviction of...

4 hours ago | Justice

A veteran of the liberation struggle is asking the High Court in Windhoek to evict eight households who set up homesteads on land in the...

Mouton to plead in 2018

4 hours ago | Justice

A young man accused of killing a police officer and two civilians while allegedly driving under the influence of alcohol in July 2015, is scheduled...

NYS cooks unhappy over zero...

4 hours ago | Labour

As part of saving costs, the National Youth Service (NYS) in December last year discontinued overtime for kitchen staff at the Rietfontein campus. However, this...

Load More