Road works well on target – RA

The Roads Authority says all construction projects are continuing without major hurdles.

03 February 2017 | Infrastructure

CATHERINE SASMAN



The Roads Authority (RA) has pointedly denied any recent work stoppages on any of the major road construction projects.

RA chief executive officer Conrad Lutombi also insists that there is sufficient budgetary provision to complete on schedule multibillion-dollar projects.

This is despite numerous phone calls from role players who have complained about non-payment and resultant delays in the resumption of work after the builders’ holiday between 15 December and 15 January.

Callers claimed that work on the N$1.085 billion second phase of the dual carriageway between Windhoek and Okahandja had started later than scheduled because of outstanding payments. The road is being built by the Namibian outfit Otesa Civil Engineering and Italian company CMC Ravenna.

Not so, said Lutombi.

“The fact of the matter is that this is a government project. There is no history in Namibia since independence where the government undertook a project and just abandoned it, especially a critical project such as [the Windhoek to] Okahandja road,” he said.

“What is happening is operational matters and those are being handled within the parameters of the project.”

Otesa director Elmo Kaiyamo was equally adamant that there has never been any work stoppage on this project. He said work continued until 16 December and resumed in January.

Kaiyamo said work picked up slowly in January because a huge value chain took time to mobilise.

DR3609

There were also complaints of an alleged downscaling of work due to non-payment since June/July on the DR3609 road from Oshakati to Omungwelune and Ongenga, which reportedly forced a reduction of 145 to 15 workers.

This 37-kilometre road is being built by the Chinese firm Zhong Mei Engineering at a cost of N$216 million. Lutombi acknowledged that a N$46 million payment was due on 19 January but he was adamant that the invoicing was being processed and payment was about to be made.

Lutombi said because work on this project was already 95% complete it was less labour-intensive than at the start when earthworks and de-bushing had to be done.

He acknowledged some delays but said these were due to protracted and complex negotiations with villagers along the route.

Lutombi said contractors were entitled to stop work should there be undue late payments. Contractually the RA must pay contractors within 56 days after they have submitted interim payment certificates.

Should a payment not be made, the contractor must give 21 days’ notice of a planned work stoppage.

UNAUTHORISED, UNBUDGETED PROJECTS

Sources maintain that payments have been sluggish because the RA has “overcommitted” on projects on behalf of the government because of a lack of proper management and planning.

“No project should be committed without the assurance of finance,” one source said. “Right now the RA finds itself with many debts which the CEO [Lutombi] openly denies.”

Finance minister Calle Schlettwein last week stated that some major road projects – including the more than N$1 billion second phase of the Windhoek to Okahandja road, the N$900 million first phase of the Windhoek to Hosea Kutako International Airport dual carriageway, as well as the yet-to-be-designed Uis to Khorixas-Kamanjab road – had not been budgeted for or authorised.

The RA’s commitment to such projects has forced the government’s hand to free some N$450 million from the Road Fund Administration (RFA) despite the fact that there was no such provision in the RFA’s five-year business plan for the period April 2017 to March 2022.

The business plan only makes provision for new developments, rehabilitation and maintenance. However, as far as Lutombi is concerned the RFA was supposed to make provision for “economic roads” as well.

“The only reason why the RFA is only covering maintenance is because the collection of revenue is not much,” he said.

Schlettwein issued a stern warning that he would invoke Section 17 of the Finance Act - in other words that the state would not pay for any further unauthorised expenditure.

According to Lutombi, however, the RA has made budgetary provision “under the RFA budget”.

“As far as this financial year [which ends on 31 March] is concerned we have no problem; the work will continue until April. The critical one is whether we have funding for the next financial year and we do have that funding. We have budgeted under RFA funding for the next financial year moving forward,” Lutombi said.

Similar News

 

Patience of the people running out - Kazapua

20 hours ago | Infrastructure

Windhoek mayor Muesee Kazapua says the patience of Namibians is running out when it comes to land delivery.Speaking at a groundbreaking ceremony yesterday in Windhoek's...

RCC, Chinese deal declared invalid

1 day - 23 May 2018 | Infrastructure

Government has declared an agreement between the Roads Contractor Company (RCC) and Chinese firm Jiangsu Nantong Sanjian invalid and unenforceable by law. The RCC recently...

One brick at a time

1 week ago - 14 May 2018 | Infrastructure

The unveiling of 20 low-income houses over the weekend built by the Mariental Shack Dwellers’ Federation’s team of which more than 80% were women, highlighted...

Omukuli tagu pewa RCC kehangano lyaChina kagu li paveta

1 week ago - 14 May 2018 | Infrastructure

Ominista yEmona lyaNamibia, Calle Schlettwein okwa popi kutya omilandu dhiikwaveta inadhi landulwa pethimbo lyetsokumwe lyomukuli gwoomiliyona 570 pokati kehangano lyoRoad Construction Company (RCC) oshowo ehangano...

N$530m road unlocks new opportunities

2 weeks ago - 07 May 2018 | Infrastructure

Otjozondjupa governor Otto Iipinge has welcomed the completion of the Okamatapati-Grootfontein road that was inaugurated by President Hage Geingob at Grootfontein on Friday, saying that...

N$4 million for Opuwo-Omakange road repair

3 weeks ago - 02 May 2018 | Infrastructure

OPUWO – A total of N$4 million has been budgeted for the repair of the road between Opuwo and Omakange in the Kunene Region, chief...

RFA reserves fund arrears millions

4 weeks ago - 26 April 2018 | Infrastructure

Jo-Maré Duddy – More than N$317.7 million was paid from the reserves of the Road Fund Administration (RFA) in its 2016/17 financial year to cover...

Taskforce for B1, B2

1 month - 24 April 2018 | Infrastructure

One of the priorities for the transport ministry during the current financial year is the establishment of a taskforce for the B1 and B2 highways,...

Fuel storage ready by June

1 month - 23 April 2018 | Infrastructure

As the Walvis Bay bulk fuel storage project nears completion, details still remain sketchy about who will manage the N$5.6 billion facility, as well as...

N$1bn Chinese grant for airport road

1 month - 13 April 2018 | Infrastructure

The Chinese government will provide N$1.1 billion in financing for the construction of the road leading from Windhoek to Hosea Kutako International Airport.In an exclusive...

Latest News

Rent battle intensifies

20 hours ago | Government

Rent control boards that protected tenants from exploitation by property owners during the apartheid era are still implementable in Namibia and are not unconstitutional.This was...

RCC thought they could get...

20 hours ago | Government

A ministerial technical committee has been tasked to urgently compile a dossier for cabinet, with recommendations on disciplinary action and the way forward for the...

Skorpion’s production steady in 2017

20 hours ago | Business

Jo-Maré Duddy – Vedanta Zinc International’s wholly-owned Skorpion Zinc mine near Rosh Pinah in Namibia produced 84 000 tonnes of refined metal in its financial...

What will make or break...

20 hours ago | Columns

Here are 13 tips for starting a business and making it succeed.1. Know yourself, your true motivational level, the amount of money...

Taking NWR to another level...

20 hours ago | People

hen and protect the financial condition of the company,” said Talita Horn, chief financial officer at NWR. Talita Horn did consulting and assurance work...

Informal sector exploits workers

20 hours ago | Labour

Namibia faces key developmental challenges such as a growing informal economy, lack of decent and secure jobs and insufficient social protection for workers.However, employment created...

Africa briefs

20 hours ago | Economics

South Africa's outlook for tax revenues unchangedSouth Africa finance minister Nhlanhla Nene said on Tuesday that the outlook for tax revenues remain unchanged, in a...

The man behind the Katoshe...

20 hours ago | People

Gabby Tjiroze - His future was unpredictable and hard to imagine, but today he is the mastermind behind Katoshe D30 - a mobile phone that...

Don't compromise security - Tsowaseb

20 hours ago | People

The Namibia Statistics Agency (NSA) has many priorities and security is definitely at the top of the list. Careers spoke to NSA security manager Titus...

Load More