NHE fails to build houses

13 September 2017 | Infrastructure

President Hage Geingob is accused of having “misled” the Namibian nation by claiming during his 2017 state of the nation address (SONA) that more than 5 000 houses had been built with public money during the previous financial year.

During his SONA address in April, Geingob boasted that 5 554 houses had been completed nationwide in the first year of implementation of the Harambee Prosperity Plan, which was in 2016.

However, the National Housing Enterprise (NHE), which has as its core mandate the construction of affordable housing, has acknowledged that not a single new house has been built by the parastatal since the departure of beleaguered former CEO Vinson Hailulu in August 2015.

President Geingob's Harambee Prosperity Plan (HPP) had estimated that 20 000 houses would have been built, 27 000 plots serviced and 50 000 rural toilets installed to replace the bucket system by the end of 2017.

NHE spokesperson Eric Libongani this week confirmed that the parastatal had “not executed its own housing project” since around August 2015, admitting that the NHE had not embarked on any new housing projects since then.

However, Libongani said the NHE had been “working towards a new housing project model through Request for Proposals (RFP) in which the NHE will engage with private-sector companies in financing and construction of houses across Namibia”.

He said 54 bidders had so far submitted proposals and the first phase of this construction project was at an advanced stage.



Last year, the NHE announced that the RFP model would deliver 5 000 houses at an estimated cost of N$2 billion. By then, a number of Chinese and other companies had submitted their bids.

Libongani said during the first phase of the project the NHE envisaged the delivery of more than 400 houses. It is not yet clear who the bidders are.

NHE insiders who preferred anonymity said they were embittered about the slow delivery of housing and the stoppage of the mass housing project. They said the NHE during Hailulu's tenure had built 3 500 houses under the mass housing project in about 10 to 11 months.

“If the project had been properly funded and not politicised, the NHE might have been in a position to build as many as 20 000 houses,” said one, adding: “Africa is the enemy of its own development. We value politics more than we value economics.”

The insiders acknowledged that the mass housing project did experience “teething problems” but insisted that it nonetheless employed 4 880 workers who on average earned at least N$4 000 per month, which they said meant that around 25 000 people directly benefitted from the programme.



Unallocated houses

The government, and in particular the Ministry of Urban and Rural Development, is said to be failing to distribute the houses that the NHE had built before the middle of 2015.

At the end of July this year, a whopping 87% of credit-linked houses bought through loans were unoccupied; only 31% of heavily subsidised social housing was occupied.

President Geingob made mention of this in his 2017 SONA address when he noted that “some houses remained unoccupied for too long due to the bureaucratic process involved in the transfer of ownership of land”.

Geingob then mentioned that his administration was following up on these cases and working with partners to expedite the process.

That is what the president said on 12 April, and on 24 April his office sent a letter to the NHE with a request to develop and submit an action plan to deal with unallocated housing units built under the mass housing project.

Geingob had already communicated with the minister of urban and rural development, Sophia Shaningwa, on the unallocated houses in January and Shaningwa informed her staff to expedite the allocation of the houses.

It is understood that the ministry has taken over the role from the NHE to allocate the houses.

CATHERINE SASMAN

Similar News

 

No pay, no work, says Salini

1 day - 18 September 2017 | Infrastructure

The Neckartal Dam contractors will not resume construction activities until it is paid an overdue bill of N$600 million for work completed over the last...

PPP sought for Keetmans housing

5 days ago - 14 September 2017 | Infrastructure

In line with cost-cutting in tough economic times, the urban and rural development ministry, along with the Keetmanshoop Municipality, are looking into public-private partnerships to...

NHE fails to build houses

6 days ago - 13 September 2017 | Infrastructure

President Hage Geingob is accused of having “misled” the Namibian nation by claiming during his 2017 state of the nation address (SONA) that more than...

NHE boss sniffs at PPP model

2 weeks ago - 31 August 2017 | Infrastructure

National Housing Enterprise (NHE) chief executive officer Gisbertus Mukulu says as long as private developers service land and build houses, property prices will remain high.Talking...

NDP5 taken to Hardap

1 month - 31 July 2017 | Infrastructure

The deputy minister of economic planning, Lucia Iipumbu last week visited Mariental in the Hardap Region as part of the National Planning Commission's (NPC) popularisation...

Hardap alleviates Neckartal water woes

1 month - 25 July 2017 | Infrastructure

STAFF REPORTERNamWater will funnel crucial water from the Hardap Dam to the Neckartal Dam construction site in order to alleviate critical water shortages there and...

Desert Rose EIA under scrutiny

1 month - 25 July 2017 | Infrastructure

The developers of the Desert Rose project are keen to get the project rolling, having recently submitted an environmental impact assessment (EIA) for the N$8-billion...

Chinese firms stop work amid financial woes

1 month - 24 July 2017 | Infrastructure

Two Chinese companies responsible for the bulk earthworks for the construction of the railway line between Ondangwa and Oshakati have reportedly stopped work due to...

Dunes Mall nearly done

2 months ago - 21 July 2017 | Infrastructure

The construction of the Dunes Mall with an estimated value of N$650 million in the vicinity of the Diaz Circle in Walvis Bay is on...

Millions for new port gate

2 months ago - 21 July 2017 | Infrastructure

Namport intends to start with the construction of a new port entrance gate and truck staging area at a cost of approximately N$40 million in...

Latest News

Chinese labour on cement project...

22 hours ago | Labour

Whale Rock Cement, currently building the second cement factory outside Otjiwarongo, says it will retain 150 out of 400 Chinese workers when the construction phase...

Chicken-stealing neighbour arrested

22 hours ago | Crime

KENYA KAMBOWE The Omusati police have arrested a 25-year-old man from Omagalanga village in the Oshikuku constituency who allegedly stole and slaughtered about 20...

Teen dies after jumping from...

22 hours ago | Crime

JANA-MARI SMITH Ondangwa police are investigating a case of culpable homicide after a 13-year-old boy died when he jumped out...

Murder accused a no-show at...

22 hours ago | Justice

A 50-year-old man from Karasburg, who is accused of killing his girlfriend, failed to turn up at the start of his trial where he also...

BIG back on the cards

22 hours ago | Social Issues

There is proof that a basic-income grant can improve the lives of people, says the special advisor to the minister of poverty eradication and social...

Swakop considering by-law on plastic...

22 hours ago | Environment

The Swakopmund Municipality is planning on introducing a by-law which will compel shops to only stock reusable shopping bags, instead of the current lightweight bags...

Ambassador to hand over health...

22 hours ago | Health

The United States Ambassador to Namibia, Thomas Daughton, will today hand over prefabricated containers at the Nkurenkuru Health Centre in the Kavango West Region.Daughton will...

VP attends Oshipe festival

22 hours ago | Cultural

Launched early this year by President Hage Geingob, Operation Tulongeni which was aimed at encouraging farmers to start working their fields following good rains, was...

Amunyela: Swapo needs business voice

22 hours ago | Politics

Businessman Desmond Amunyela believes the ruling Swapo party needs to focus more on economic policy given the challenges facing the country. Amunyela, who is a...

Load More