Foreigners dominate bids

Chinese, Indian, Turkish, Spanish, Portuguese, Botswana and South African firms are among those in line to rake in billion-dollar Namibian tenders.

26 February 2019 | Infrastructure

A total of 25 companies have been shortlisted for the construction and upgrade of the Walvis Bay-Kranzberg railway line and the construction of a new road to Hosea Kutako International Airport.

A Chinese firm, China Harbor Engineering Company, was shortlisted for both projects.

It submitted a joint bid with local company Roadhart CC for the rail project. The other local company to be selected for the rail project is D&M Rail. It submitted a joint bid with China Jiangxi and China Henan.

Only two local companies were shortlisted for the airport road project - NCR and Top International Engineering Namibia. The other companies shortlisted include Portuguese, Spanish and Indian firms, while 12 Chinese companies complete the list.

In total 16 firms were shortlisted for the airport road and nine for the railway project, with 17 Chinese companies featuring either as sole bidders or in joint ventures with others. D&M Rail Construction was appointed in 2014 by TransNamib to rehabilitate the Kranzberg-Tsumeb railway line in a deal worth N$200 million, The Namibian reported.

The African Development Bank (AfDB) initially required companies to have an average turnover of N$631 million, which effectively excluded local firms. Companies were also required to have a monthly cash flow of N$53 million.

These requirements were relaxed after finance minister Calle Schlettwein intervened.

Roads Authority CEO Conrad Lutombi would not comment when approached for comment.

Works ministry executive director Willem Goeiemann told Namibian Sun that the process of selecting a contractor was still ongoing.

“We are not done yet, we have not even briefed the ministers. The process is not complete,” Goeiemann said briefly.

Both projects are being partially funded by the African Development Bank through a N$2 billion loan granted in December 2017.

Last year the Construction Industry Federation (CIF) asked the government to lobby the AfDB to relax the requirements set for the two tenders.

“The tender requirements... are of such a nature that they automatically preclude all Namibian contractors,” said CIF general secretary Bärbel Kirchner.





The upgrading of the railway track between Walvis Bay and Kranzberg would speed up freight and passenger traffic.

The current railway, of Cape Gauge standard, was last upgraded in the 1960s and, in its current condition with speed restrictions, is an infrastructure bottleneck, resulting in increased transport costs.

After improvement, freight trains will be able to travel at up to 80 km/h and passengers will enjoy speeds of up to 100 km/h. The rail upgrading will be done over three years.

As for the planned airport road, a new dual carriageway with two lanes in each direction, which will incorporate an option for a third lane in the future, will be constructed over a period of 42 months. The existing road will be retained as an alternative to service local traffic.

The Chinese government has granted N$10 billion in infrastructure funding to the Namibian government through its Belt and Road initiative. If taken up by the government, a portion of that would finance the planned upgrading of Hosea Kutako International Airport.

OGONE TLHAGE

Similar News

 

Unfinished pipeline impacts 7 000 residents

1 day - 20 March 2019 | Infrastructure

About 6 932 people and 33 790 large and 18 395 small stock units are facing thirst, as the agriculture ministry battles to finish the...

DBN pushes affordable homes

1 week ago - 11 March 2019 | Infrastructure

Fast-tracking residential land delivery and affordable housing will not only empower cash-strapped low-income earners and ensure them a stake in the local economy, but lead...

Hold-up on highways

1 week ago - 11 March 2019 | Infrastructure

Major sections of the Okahandja dual carriageway and the road from Windhoek to Hosea Kutako International Airport are yet to be completed.Works minister John Mutorwa...

Engineers, builders to pay for RA building repairs

2 weeks ago - 01 March 2019 | Infrastructure

The consulting engineering firm and the building contractor Namibia Construction will have to foot the bill for repairs to the Roads Authority’s new N$219 million...

GIPF pumps millions into housing at Eenhana

3 weeks ago - 28 February 2019 | Infrastructure

The Government Institutions Pension Fund (GIPF) has invested N$17.4 million in housing aimed at low- and medium- income groups at Eenhana in the Ohangwena region.According...

Oopoloyeka mbali dhomoshilongo dha talika unene omeho komahangano gopondje...

3 weeks ago - 28 February 2019 | Infrastructure

OGONE TLHAGEEhangano lyaChina lyoChina Harbor Engineering Company, olya tulwa momusholondondo gwokulonga oopoloyeka adhihe dhoka mbali.Ehangano ndyoka olya ningi eindilo lyiimanga kumwe nehangano lyomoshilongo lyoRoadhart CC...

Foreigners dominate bids

3 weeks ago - 26 February 2019 | Infrastructure

A total of 25 companies have been shortlisted for the construction and upgrade of the Walvis Bay-Kranzberg railway line and the construction of a new...

N$500 million bailout for RA

3 weeks ago - 25 February 2019 | Infrastructure

The Road Fund Administration (RFA) has bailed out the Roads Authority (RA) to the tune of N$500 million, so the ailing parastatal can settle outstanding...

First Lady enters shack fray

4 weeks ago - 20 February 2019 | Infrastructure

First Lady Monica Geingos has reached out to experts to bring their ideas on how to solve the housing crisis to the attention of policymakers....

Omunyekadhi a nongonona uupyakadhi woombashu

4 weeks ago - 20 February 2019 | Infrastructure

Etalelepo kolukanda hoka taku yambulwapo opoloyeka yomagumbo moFreedom Square moGobabis, lya landula koonkundathana naGeingos odha etitha omukumo kutya epangelo olyiitulamo mokweendelelitha onkalo yekandulepo lyompumbwe yomagumbo...

Latest News

Millions unaccounted for at NDC,...

1 day - 20 March 2019 | Economics

The Namibia Development Corporation (NDC) has failed to submit documentary evidence to prove how it spent N$90.1 million between 2015 and 2017, the latest report...

Aluta continua!

1 day - 20 March 2019 | Columns

Tomorrow is without doubt a significant day in our national history, as we pause to celebrate the spirit of our forefathers and struggle heroes and...

Africa Briefs

1 day - 20 March 2019 | Economics

No end date for Eskom’s power cutsSouth Africa's public enterprises Minister Pravin Gordhan said yesterday he cannot say yet when rolling blackouts will end, as...

Cob plundering suspects nabbed

1 day - 20 March 2019 | Crime

Leandrea Louw Two men arrested on Saturday for allegedly being in possession of 60 large cob made their first appearance in the Walvis Bay Magistrate’s...

Unfinished pipeline impacts 7 000...

1 day - 20 March 2019 | Infrastructure

About 6 932 people and 33 790 large and 18 395 small stock units are facing thirst, as the agriculture ministry battles to finish the...

Apple unveils new iPad, updates...

1 day - 20 March 2019 | Technology

Sonam RaiApple Inc, in a surprise move on Monday, launched a new 10.5-inch iPad Air and updated its iPad Mini ahead of a March 25...

Climate change and productivity

1 day - 20 March 2019 | Agriculture

Climate change is a long-term change in climatic/weather patterns of the earth or region. Such change is observed in temperature and rainfall patterns, amongst others....

Palladium hits record high

1 day - 20 March 2019 | Business

Palladium surged to a record yesterday as the risk of a ban on some Russian exports added to supply concerns for the autocatalyst metal. Spot...

State supports non-compliant security firms

1 day - 20 March 2019 | Business

Employers and trade unions agree that one of the major issues facing the Namibian security services industry is that some government institutions continue to appoint...

Load More