Etango earthworks near done

Nearing completion
560 workers, 1.1 million safe hours and earthworks 92% complete as Etango early works track to budget
Ogone Tlhage
Bannerman Energy says construction early works at its Etango uranium project in Namibia are tracking on budget and schedule, with bulk earthworks 92% complete and the site workforc
...